Interim Care & Maintenance phase: what it means and why it matters

Imperial is sharing information and seeking your feedback on Imperial’s Interim Care & Maintenance (IC&M) plans to inform how water, wildlife, waste, and community engagement will be managed during this phase of the project.

In this article

Overview

Planning for final closure through the Mackenzie Valley Environmental Impact Review Board's Environmental Assessment process is expected to take several years. During this time, the site will remain in Interim Care and Maintenance (IC&M), which helps bridge the gap between the end of production and the start of closure work. This allows Imperial to continue important monitoring, maintenance, and planning activities while the closure process moves forward.

Imperial's current operating approvals from the Canada Energy Regulator and the Sahtú Land and Water Board expire in May 2028. To continue carrying out IC&M activities after that date, Imperial will need to apply for new regulatory approvals. Work is underway to prepare these applications, with submissions planned for January 2027.

Communities and organizations in the Sahtú region have previously emphasized the importance of early engagement on regulatory applications. In response, Imperial is sharing and discussing selected IC&M management plans with communities before they are submitted to regulators, so feedback can be considered early in the process.

How to provide feedback

In addition to ongoing direct engagements with Sahtú communities and organizations, written submissions on the IC&M management plans can be sent to normanwellscommunity@esso.ca.

Click on the icons below to learn about the critical work included during the IC&M phase:

Keeping wells safe


Continue well suspension and early abandonments, physically sealing wells and preventing potential pathways between the reservoir and the surface, reducing long-term environmental risk.

Protecting water and the environment


Key environmental monitoring programs will continue during IC&M, including the Aquatic Effects Monitoring Program. These programs monitor the Mackenzie River, fish health, ground water, and surface water quality. Ongoing monitoring helps maintain continuous data, identify trends, and detect potential issues early.

Closure takes time


The MVEIRB-led Closure Environmental Assessment will take several years. IC&M allows Imperial to responsibly manage the site while the closure regulatory process is underway anticipated for approximately three to seven years.

Continued site presence


Even after operations stop, Imperial will maintain a local presence in Norman Wells to watch over the facilities, environment and maintain personnel and public safety.

Supports closure planning


Advancing environmental site assessments will help better understand historical impacts in the soil and groundwater across the site to support final closure and reclamation planning. When operations end, more areas will become available for assessment. This work will inform remediation needs and inform development of a final closure plan.

Activities during the IC&M period:

To learn more about the decommissioning activities happening on-site, watch our Closing a Century short video series.

  • Environmental monitoring


    Environmental monitoring, including water quality (surface and groundwater), aquatic life and wildlife monitoring around the facility.

  • Water use (Mackenzie River)


    Anticipating an 85% reduction in water use from operations. Imperial will continue using water from the Mackenzie River, primarily for ice road construction once production operations ends.

  • Progressive Remediation & Reclamation


    Progressive remediation and reclamation activities will continue in identified impacted areas and are intended to reduce potential risks to the surrounding environment and complement future closure requirements based on the outcomes of the Closure EA.

  • Well suspensions and abandonments


    Well suspensions and abandonments, to seal and secure wells, installing plugs and barriers prior to final closure and reclamation.

  • Waste management


    Although the site will no longer be in an operating state, active waste management will continue including safe storage and disposal activities.

  • Early demolition


    Imperial will advance early demolition activities; early demolition removes surface infrastructure to open up the footprint to assess historical contamination, informing final closure planning, and remediation efforts in the 2030s+.

  • Fuel terminal operations


    Ongoing fuel terminal operations under existing permits, with no anticipated interruption to diesel supply and jet fuel for the region.

  • Emergency response planning


    Emergency response planning will continue, including planning for potential wildfires in the region and the associated response measures.

    Information sheets


      Engagement process

      Overview

      Imperial is engaging Sahtú communities and organizations to share information on the IC&M phase and gather feedback to inform the IC&M application. 

      Desired outcome – IC&M management and engagement plans developed in collaboration with Sahtú communities and submitted to the CER and SLWB.


      Click on the status bar to learn about the different phases of the IC&M application engagement process and access select management plans:

      Overview of IC&M phase and engagement process


      IC&M Phase 1 engagement summary – coming soon!

      Norman Wells closure

      The closure project is a decades-long, community-involved process that prioritizes safety, environmental care, and Northern and Indigenous benefits.