selected item
2 min read
Sarnia Products Pipeline (SPPL) Segments Mitigation Project
2 min read
Keeping fuel moving safely across southern Ontario
Imperial is applying to the Ontario Energy Board (OEB) for an order granting leave to construct improvements to a section of Imperial’s Sarnia Products Pipeline (SPPL), which helps transport gasoline, diesel, and jet fuel from Sarnia to communities and businesses across Southern Ontario, including the Greater Toronto Area.
The proposed project is intended to ensure the long-term safety and reliability of the SPPL while providing a stable supply of transportation fuels for homes, businesses, airports, and essential services.
Why is this project needed?
The SPPL has been operating safely for decades and is a key part of Ontario's energy infrastructure.
As part of Imperial’s ongoing pipeline integrity and maintenance program, we identified a short section of pipeline near Millgrove and Waterdown that has reached the end of its planned service life and we’re taking proactive steps to support safe and reliable operation going forward.
What does the project involve?
The project includes:
- Installing a new 12-inch pipeline connection between an existing Millgrove valve station and a new pump station near Millgrove Junction; and
- Installing two new sections of 12-inch pipeline that will connect the new pump station near Millgrove Junction to the existing Waterdown-to-Finch pipeline.
These upgrades will allow the pipeline system to continue operating safely and efficiently while integrating with newer pipeline infrastructure that was upgraded in recent years. By improving the reliability of the pipeline system, the project will help maintain access to the fuels that people and businesses depend on every day.
Project timeline
Subject to regulatory and permitting approvals, current project timing is as follows:
| Milestone | Timing |
| Regulatory review and approvals | 2026-2027 |
| Construction begins | May 2027 |
| Construction completed | September 2027 |
| Project commissioning and start-up | Following construction activities |
Ontario Energy Board application – File: EB-2026-0263
The full application and evidence filed with the OEB for the project, along with the OEB’s Notice of a Hearing, are listed below:
- Application and Evidence filed with the OEB on October 13, 2026
- Appendix 1 to the Application and Evidence (Environmental Report) filed with the OEB on October 13, 2026
- Notice of a Hearing issued by the OEB on November 6, 2026
- Notice of a Hearing (French) issued by the OEB on November 6, 2026